CH&PA: Mohamed’s ‘grossly overpriced’ Versailles-Parika Highway claim ‘overly simplistic’

Opposition Leader Azruddin Mohamed’s claim that the proposed Versailles-to-Parika Four-Lane Highway is “grossly overpriced” rests on a flawed comparison that ignores vast differences in scale between it and the completed Eccles-to-Great Diamond highway, the Central Housing and Planning Authority (CH&PA) said.

 

Mohamed had measured the Region 3 project, estimated at approximately $121 billion, against the $13.3 billion cost of the Region 4 highway. But the $13.3 billion figure represents a completed contract, while the Region 3 estimate covers a project yet to be awarded, CH&PA said, adding that the comparison also fails to account for major differences in engineering requirements and scope.

The Region 3 highway spans approximately 20.74km, compared with 8.6km in Region 4 – about 2.4 times the length. Its preparation base width, at 53.15m, is more than double the 25.99m used in Region 4, producing a preparation footprint nearly five times larger.

The projects also differ sharply in ancillary works. Region 3 includes approximately 68.02km of access-road construction, versus 0.8km in Region 4, and 62 bridges compared with 40, with a combined bridge length about 2.7 times greater. Region 3 further includes 3.82km of revetment works and more than 31,100 linear metres of Prefabricated Vertical Drains (PVDs) for ground improvement, neither of which formed part of the Region 4 scope.

A simplistic per-kilometre calculation would put Region 4 at roughly $1.55 billion per kilometre against $5.21 billion for Region 3, but this understates what the larger project finances, CH&PA said, since the $108 billion budget covers an integrated programme of road, bridge, drainage and ground-improvement works, not the main carriageway alone.

The timing of the two projects also differs, with Eccles-to-Great Diamond completed in 2023 and Versailles-to-Parika being costed under 2026 construction prices for labour, fuel, sand, cement, steel and other inputs.

Given the differences in length, scale and engineering scope, along with the several-year gap between the two projects, the comparison does not provide a sound basis for describing the Versailles-to-Parika Highway as “overpriced,” CH&PA said.

Opposition Leader Azruddin Mohamed
Opposition Leader Azruddin Mohamed

Leave a Reply

Your email address will not be published. Required fields are marked *


About us

At Ignite News Inc., we are committed to delivering unbiased, accurate, and real-time news to the people of Guyana and beyond. Rooted in integrity, we strive to uphold the highest standards of journalism—ensuring every story we publish is factual, transparent, and free from bias. In an era of misinformation, our mission is to provide clarity and empower our readers to form their own opinions. We champion freedom of expression, cultural respect, and accountability, adapting to the ever-changing media landscape to better serve our audience. At Ignite News, truth is our foundation, and trust is our commitment.


CONTACT US

CALL US ANYTIME



Newsletter



    Categories