Parliament has approved an additional G$24.7 billion for the first phase of Guyana's Gas-to-Energy project, pushing its overall cost beyond US$900 million, with Prime Minister Mark Phillips assuring the National Assembly that the Government does not anticipate needing further funding to complete the development.
The additional allocation was considered on Monday, November 23, during the Committee of Supply's examination of supplementary estimates under the Office of the Prime Minister.
Responding to questions about whether the latest allocation would be sufficient to complete the project, Phillips acknowledged that he could not predict every eventuality but expressed confidence that no further financial provisions would be necessary.
"Mr Speaker, I am not clairvoyant, but I'm confident," the Prime Minister told the House.
The G$24.69 billion allocation forms part of a wider G$89.8 billion supplementary spending request tabled by Finance Minister Dr Ashni Singh last week.
The latest funding comes on top of previous budgetary allocations and supplementary provisions for the project, which is being developed at Wales, West Bank Demerara.
During the parliamentary examination, Phillips confirmed that the revised overall cost of the initial phase now exceeds US$900 million.
The Gas-to-Energy project is a major component of the Government's plan to expand electricity generation and reduce the country's dependence on imported fuel.
Its first phase includes a 300-megawatt power plant and a natural gas liquids facility, with natural gas to be transported from offshore production operations to Wales.
According to the latest timeline outlined by the Government, the first gas turbine is expected to begin delivering electricity to the national grid by the end of December 2026.
All gas turbines are scheduled to be fully commissioned during the first quarter of 2027.
The project has experienced delays and required additional funding since its initial announcement, raising questions about its final cost and completion timeline.
However, Phillips maintained that the Government remains confident the latest allocation will be sufficient to bring the first phase to completion.