About 701 households in Leguan are now receiving treated water from a $687 million treatment plant, with plans to extend the supply to other communities on the island.
The facility, commissioned by President Dr Irfaan Ali on Sunday, can produce two million litres of treated water daily. However, residents of the community of Success on the island are still awaiting a transmission line to connect them to the plant. Ali said residents raised the need for the connection during his visit to the island last week, and he hopes it will be completed within a month.


Guyana Water Inc. (GWI) Chief Executive Officer Shaik Baksh said the utility also plans to begin laying larger mains in January to improve water pressure and extend the treated supply across Leguan.

For households already connected, the new facility is expected to improve water quality by reducing iron content, which has caused staining on tiles and household fixtures.
The Department of Public Information said the plant is the first in Guyana equipped with an activated carbon filter tank. Baksh said the filtration system also improves the water's taste and clarity.
The commissioning follows several years of investment in water treatment infrastructure. Public Utilities and Aviation Minister Deodat Indar said in September that seven new treatment plants had been constructed over the past five years, while 12 existing facilities were upgraded.

Previous openings included plants at Parika and Wales in 2025, and Five Miles, Bartica, in February 2026.
Leguan is the first of five new plants to be commissioned under the government's Water Supply Improvement Project. The remaining facilities are planned for Wakenaam, Maria's Delight, Bath and Adventure.


GWI is also planning a water refill station at the Leguan plant, where residents will be able to purchase five gallons of water for $100, compared with the $700 they reportedly currently pay.
Baksh said work on the station would begin shortly, but no opening date has been announced.

Source: GWI/FB