The Government is seeking an additional $24.7 billion for its Gas-to-Energy project as work continues on the major initiative aimed at expanding electricity generation and reducing the cost of power in Guyana.
The funding is being sought under the Office of the Prime Minister as part of supplementary financial papers totalling $89.8 billion presented to the National Assembly on Wednesday by Finance Minister Dr Ashni Singh. It will be debated at the next sitting.
The additional allocation comes after approximately $258.1 billion had already been spent on the project by the end of 2025, according to the Auditor General's report.
The Gas-to-Energy initiative involves transporting natural gas from the Liza field offshore to Wales, West Bank Demerara, where it will be processed and used to generate electricity.
The project includes a natural gas pipeline, a natural gas liquids processing plant and a power plant with an expected generation capacity of approximately 300 megawatts.
The Government has said the initiative is expected to significantly expand the country's electricity generation capacity, reduce reliance on more expensive imported fuel and ultimately lower electricity costs for consumers.
The 2025 Auditor General's report shows that expenditure on the project totalled $258.1 billion by December 31, 2025. This included $24.6 billion in 2022, $48.3 billion in 2023, $105.3 billion in 2024 and $79.3 billion in 2025.
For 2026, the Government had initially budgeted $10.7 billion for the project. The latest $24.7 billion supplementary request would provide additional resources beyond that original allocation.
The project has experienced construction delays and adjustments to its implementation timeline. Initially expected to begin delivering electricity by the end of 2024, it is now targeted to deliver first power by the end of 2026.
In May, the Government also announced a settlement with contractor Lindsayca Guyana Inc. following disputes relating to soil stabilisation works and delays. The settlement increased the original US$759 million contract sum by 12.8 per cent.
The supplementary allocation is intended to support the continued advancement of the project as Government works towards bringing the facility into operation.