Work on Mackenzie/Wismar Bridge ahead of schedule
Ongoing works on the New Wismar/Mackenzie Bridge (DPI photo)

Work on Mackenzie/Wismar Bridge ahead of schedule

Works on the US$35 million Mackenzie/Wismar Bridge are advancing swiftly and remain well ahead of schedule. According to a report provided by the Ministry of Public Works on Monday, the overall physical works are now 83.5 per cent complete.

Another section of the bridge under construction (DPI photo)

The 220-metre-long precast concrete bridge will significantly reduce traffic congestion and lengthy delays that have plagued commuters for years. This landmark development will mirror the design of the new Bharrat Jagdeo Demerara River Bridge.
Contractor China Railway Construction (Caribbean) Co Ltd is ahead of schedule, having already made 26 precast concrete girders, which are large beams used to support bridges and other structures.
Construction of the temporary embankment and access pathway for girder transportation has been completed, while assembly of the girder launcher has started and is approximately one week ahead of schedule.
Backfilling of the P6 abutment has been completed, and settlement monitoring is underway. Shaping of the embankment and placement of rockfill on the riverside toe piles at P6 have been partially completed.
Reinforcement and formwork placement for the P0 abutment wing and backwall are ongoing. Piers P3, P4, and P5 are fully completed, with only minor surface irregularities awaiting maintenance.
Pile cap construction at P1 and P2 is ongoing, but has encountered a three-week delay. However, this delay is not on the critical path, and sufficient programme float remains to absorb it without affecting the overall completion timeline.
For context: P stands for Pier, the vertical supports that hold up a bridge, or sometimes Pier/Abutment, depending on where it is located. The numbers (0–6) identify each pier or abutment’s position along the bridge, starting from one end.
Upon completion, the bridge will feature a prestressed, post-tensioned concrete box girder design, comprising four vehicular lanes and two barrier-separated pedestrian walkways. It will also accommodate the uninterrupted passage of hopper barges.
Importantly, the bridge will enhance connectivity and efficiency in Region Ten, positioning it as a key hub for international commerce and economic growth. (DPI)

Leave a Reply

Your email address will not be published. Required fields are marked *


About us

At Ignite News Inc., we are committed to delivering unbiased, accurate, and real-time news to the people of Guyana and beyond. Rooted in integrity, we strive to uphold the highest standards of journalism—ensuring every story we publish is factual, transparent, and free from bias. In an era of misinformation, our mission is to provide clarity and empower our readers to form their own opinions. We champion freedom of expression, cultural respect, and accountability, adapting to the ever-changing media landscape to better serve our audience. At Ignite News, truth is our foundation, and trust is our commitment.


CONTACT US

CALL US ANYTIME



Newsletter



    Categories