The prospect of losing more than US$300 million annually in fuel savings drove the Government's decision to settle with Gas-to-Energy contractor Lindsayca for US$200 million rather than face years of arbitration.

Vice President Dr Bharrat Jagdeo gave the explanation on Thursday evening while addressing the Guyana Manufacturing and Services Association's (GMSA) 31st Annual Presentation Awards and Dinner at the Marriott Hotel.

He said the dispute centred primarily on road construction and site preparation, both of which were ExxonMobil's responsibilities during the pre-project phase.
"Their fundamental claim was that the road that we were building, that Exxon was responsible for in the pre-project era, that that was not ready on time and of the quality. We disputed that. We believe that's not true," Jagdeo said.

The contractor also raised concerns about the additional work required to prepare the site.

Despite disputing the claims, the Government reconsidered its intention to pursue arbitration after a decision by the Dispute Avoidance and Adjudication Board.

"We then decided that if we were to pursue the arbitration, it would take several years more and that our best bet would be to negotiate, because if we had gone to the arbitration, it would lead to further delays," Jagdeo said.

He explained that importing the equivalent fuel needed to generate the project's full 300 megawatts (MW) would cost Guyana more than US$300 million annually.
The Government is already spending G$33 billion on electricity subsidies this year, while a further G$62 billion has been allocated for capital support to power infrastructure.

According to Jagdeo, electricity currently costs about 34.56 US cents per kilowatt-hour to generate, while consumers pay 23 cents. By comparison, power from the Wales facility is expected to be sold to Guyana Power and Light Inc. (GPL) at about five US cents per kilowatt-hour.

Completion of the project is becoming increasingly critical as peak electricity demand has more than doubled since 2019, recently reaching 268 MW against available generating capacity of 255 MW.

Jagdeo said about 220 MW is now expected by the end of March 2027, with the combined-cycle component anticipated around June. The project was initially expected to begin generating electricity by the end of 2024.

Earlier this week, it emerged that the Government had agreed to an additional US$200 million requested by Lindsayca, raising the estimated project cost from US$759 million to US$956 million.

During Monday's consideration of supplementary estimates in the National Assembly, Prime Minister Brigadier (Ret'd) Mark Phillips said US$130 million of the additional sum had already been paid to the contractor.

Parliament also approved G$24.7 billion in supplementary funding to support completion of Phase One and secure turbines for Phase Two of the project.

Phillips had defended the additional expenditure as necessary to avoid a stalled project or further litigation.